| LOSS ON AN INFORMATION TECHNOLOGY PROJECT
 
 
				5. In his report, the Comptroller and Auditor General drew 
				attention to a note to the Class I, Vote 1 Appropriation 
				Account. The note described a loss of £34.6 million arising from 
				a decision not to proceed with an information technology 
				project, known as Trawlerman. The project related to the 
				development of a computer system for the Defence Intelligence 
				Staff. Treasury approval for the project had been given in 
				February 1988, and in July of that year a contract, valued at 
				£32.1 million, had been awarded for the supply and installation 
				of the necessary equipment.
 
				6. The Department formally accepted the system in January 1995. 
				In the seven years between the award of the contract and 
				acceptance of the system, however, general developments in 
				information technology and in health and safety legislation 
				meant that the Trawlerman system could not meet the needs of the 
				Defence Intelligence staff. Specifically, the original 
				specification had not included a requirement for the system to 
				be capable of being linked to other computer systems, but by 
				1995 this requirement was viewed as essential. Following a 
				review to see how the system could be modernised, in November 
				1996 the Department abandoned the project.
 
				7. The Committee asked the Department what had gone wrong to 
				result in them spending £34.6 million on a computer system which 
				they never used. In evidence supplied subsequently, the 
				Department informed us that, following further investigation, 
				they had now assessed the total loss on the project to be 
				£40.7 million. They told us that the requirements for Trawlerman 
				had been determined in the mid-1980s using the best available 
				expertise there was at the time. The intelligence staff had 
				required highly secure storage and processing of information in 
				a number of discrete security compartments. It had had to be a 
				bespoke system as, in the mid-1980s, there had been nothing that 
				could have done this off-the-shelf. Indeed, the security 
				specification was so high that there was probably nothing that 
				could do it, even now. The project had been over-ambitious and 
				the Department had relied too much on what industry had told 
				them it could deliver. It had not been able to deliver those 
				things in the timescale set.The Department added that although 
				the system had eventually been brought home successfully, by the 
				time it had arrived it had been obsolete, technology had moved 
				on, the world had moved on in terms of the end of the Cold War, 
				and there were different requirements for intelligence 
				gathering. 
 
				  |