LOSS ON AN INFORMATION TECHNOLOGY PROJECT
5. In his report, the Comptroller and Auditor General drew
attention to a note to the Class I, Vote 1 Appropriation
Account. The note described a loss of £34.6 million arising from
a decision not to proceed with an information technology
project, known as Trawlerman. The project related to the
development of a computer system for the Defence Intelligence
Staff. Treasury approval for the project had been given in
February 1988, and in July of that year a contract, valued at
£32.1 million, had been awarded for the supply and installation
of the necessary equipment.
6. The Department formally accepted the system in January 1995.
In the seven years between the award of the contract and
acceptance of the system, however, general developments in
information technology and in health and safety legislation
meant that the Trawlerman system could not meet the needs of the
Defence Intelligence staff. Specifically, the original
specification had not included a requirement for the system to
be capable of being linked to other computer systems, but by
1995 this requirement was viewed as essential. Following a
review to see how the system could be modernised, in November
1996 the Department abandoned the project.
7. The Committee asked the Department what had gone wrong to
result in them spending £34.6 million on a computer system which
they never used. In evidence supplied subsequently, the
Department informed us that, following further investigation,
they had now assessed the total loss on the project to be
£40.7 million. They told us that the requirements for Trawlerman
had been determined in the mid-1980s using the best available
expertise there was at the time. The intelligence staff had
required highly secure storage and processing of information in
a number of discrete security compartments. It had had to be a
bespoke system as, in the mid-1980s, there had been nothing that
could have done this off-the-shelf. Indeed, the security
specification was so high that there was probably nothing that
could do it, even now. The project had been over-ambitious and
the Department had relied too much on what industry had told
them it could deliver. It had not been able to deliver those
things in the timescale set.The Department added that although
the system had eventually been brought home successfully, by the
time it had arrived it had been obsolete, technology had moved
on, the world had moved on in terms of the end of the Cold War,
and there were different requirements for intelligence
gathering.
|